Two numbers decide whether a system works: power and energy. Getting either wrong produces a different kind of failure.

Request a quoteAll articles

Power and energy are not the same thing

Power (kW) is the rate at which the system can deliver energy at any instant. It must exceed your largest simultaneous load, including the surge when motors start. If power is undersized, the system trips — immediately, and regardless of how much energy it holds.

Energy (kWh) is how much it can deliver in total before it needs recharging. It sets your runtime. If energy is undersized, everything works perfectly and then stops early.

A useful way to hold the distinction: power is the size of the pipe, energy is the size of the tank.

Step 1: find your peak power

List every load that can run at the same time, with its rated power. Add them up. Then add the starting surge for anything with a motor or compressor — air conditioning, refrigeration, pumps, some tools — which can be several times running current for a short period.

The result is your peak kW. The system's continuous rating should cover your sustained simultaneous load, and its peak rating should cover the surge. A PulseTrek Performance, for example, provides 8,000 W continuous against 20,000 W peak — that gap is what absorbs motor starts.

Step 2: find your energy over the run

For each load, multiply its power by the hours it actually runs, then add them up. Be honest about duty cycle: a 2 kW heater on a thermostat is not drawing 2 kW all day, and a kettle is a very large load for a very short time.

The result is your kWh per run. Then add margin for the state-of-charge cutoff — PulseTrek systems reserve 20%, so a 30 kWh pack gives you roughly 24 kWh usable.

A worked example: small construction compound

LoadPowerHoursEnergy
Two site cabins, lighting and sockets600 W106.0 kWh
Cabin heating (thermostatic, 50% duty)2,000 W1010.0 kWh
Kettle and microwave (intermittent)2,000 W0.751.5 kWh
Tool charging station400 W83.2 kWh
Security cameras and floodlights (overnight)350 W144.9 kWh
Total energy per 24 hours25.6 kWh
Peak simultaneous draw~4.2 kW

Step 3: check the recharge window

That compound needs about 25.6 kWh per day against roughly 24 kWh usable from a 30 kWh pack — so it needs a daily recharge, and the question becomes whether there is a window and a source. Shore power overnight solves it. So does a generator running two hours to recharge. So does a solar array sized for 26 kWh/day.

If there is no recharge source at all, you need enough energy for the whole deployment, which is when multiple units or a containerised system enters the conversation.

The three mistakes that cause undersized systems

Questions answered

Frequently asked questions

What size BESS do I need?

You need power (kW) greater than your largest simultaneous load including starting surge, and energy (kWh) greater than your total use between recharges. A site drawing an average 3 kW for 8 hours needs roughly 24 kWh of usable energy.

What is the difference between kW and kWh?

kW measures power — the rate energy is delivered at any instant. kWh measures energy — how much is delivered over time. Power determines what you can run; energy determines for how long.

How much battery storage do I need for backup power?

Multiply the loads you need to keep running by the hours you need them, then add margin for the state-of-charge cutoff. Backup sizing is usually driven by a short list of critical loads rather than the whole site.

How do I calculate battery storage capacity?

Sum each load's power multiplied by its operating hours, accounting honestly for duty cycle, then divide by the usable fraction of the pack — typically 80% after the state-of-charge cutoff.

Keep reading

Related pages

Get in touch

Have a question about your own site?

Tell us the site, the load and the runtime you need. Our Austin engineering team comes back with a configuration, a runtime estimate and a price.

  • Sizing and runtime estimate for your actual load
  • 120V/60Hz and 230V/50Hz configurations
  • Rental, purchase, lease and OEM enquiries all welcome
  • Buy American Act documentation available on request
  • Financing available from just $700/month